- Per tonne:
- Labour β¦18.7 (Sf 2.34)
- Materials β¦0
- Capital β¦43.5
- Energy β¦35
- Surplus β¦38.9
Whole chain per tonne: 0.5 labour hours, 700 kWh.
Formula
A.C. = w0LhSf Labour β¦18.7 Shadow wage w0 β¦16 an hour Γ Lh 0.5 hours per tonne Γ skill factor Sf 2.34 Sf for industry: training β¦45,000 against β¦45,000, queue 20 hours against 48 + Ξ£ qiPirΞ»i Materials β¦0 A raw material, with no recipe inputs. + (D + Mo)Ξ±e Capital β¦43.5 Depreciation and maintenance β¦30 per tonne Γ financing 1.45 Γ waste factor Ξ±e 1.00 Financing is interest at 6% on equipment's average value over a 15-year life. Ξ±e is 1.00 when maintenance hours and defects are on target. + Epe Energy β¦35 E 700 kWh per tonne Γ pe β¦0.05 per kWh = β¦97.2
A.V. = rP*world Accounted value β¦136 per tonne World price $70 per tonne plus freight and insurance 29.6% = P* $90.7 Γ r 1.5 crowns per US dollar Import parity: the price at the Commonwealth border for a good it could otherwise import. Observed abroad, not calculated: a wasteful producer raises only its own cost. = β¦136
Revenue = A.V. Γ Q Accounted revenue β¦19.1 m p.a. Domestic: 140,500 t Γ β¦136 = β¦19.1 m = β¦19.1 m
Surplus = (A.V. β A.C.) Γ Q β levies Accounted surplus β¦5.46 m p.a. Revenue β¦19.1 m β cost β¦97.2 Γ 140,500 t = β¦5.46 m Distributed 40% to reinvestment, 20% to the municipal aggregate and 40% swept to the Treasury. = β¦5.46 m
Made in
Output
Made from per tonne
A raw material: no recipe inputs.
Used in p.a.
-
Industrial Gases140,500 tβ¦19.1 m100%
-
Electronic Components6,586 tβ¦896,3554.69%
-
- Final domestic use 133,900 t β¦18.2 m 95.3%