- Per tonne:
- Labour β¦37.5 (Sf 2.34)
- Materials β¦546
- Capital β¦116
- Energy β¦80
- Surplus β¦44
Whole chain per tonne: 4.27 labour hours, 2,693 kWh.
Formula
A.C. = w0LhSf Labour β¦37.5 Shadow wage w0 β¦16 an hour Γ Lh 1 hours per tonne Γ skill factor Sf 2.34 Sf for industry: training β¦45,000 against β¦45,000, queue 20 hours against 48 + Ξ£ qiPirΞ»i Materials β¦546 Chemicals: 50 kg Γ $405/t Γ r 1.5 Γ border 1.06 Γ Ξ» 1.00 = β¦32.2 Pulp: 1.05 t Γ $350/t Γ r 1.5 Γ border 0.93 Γ Ξ» 1.00 = β¦514 + (D + Mo)Ξ±e Capital β¦116 Depreciation and maintenance β¦80 per tonne Γ financing 1.45 Γ waste factor Ξ±e 1.00 Financing is interest at 6% on equipment's average value over a 15-year life. Ξ±e is 1.00 when maintenance hours and defects are on target. + Epe Energy β¦80 E 1,600 kWh per tonne Γ pe β¦0.05 per kWh = β¦780
A.V. = rP*world Accounted value β¦824 per tonne World price $575 per tonne less freight and insurance 4.48% = P* $549 Γ r 1.5 crowns per US dollar Export parity: the price at the Commonwealth border for a good it sells abroad. Observed abroad, not calculated: a wasteful producer raises only its own cost. = β¦824
Revenue = A.V. Γ Q Accounted revenue β¦972 m p.a. Domestic: 983,500 t Γ β¦824 = β¦810 m Exports: 196,700 t Γ β¦824 = β¦162 m = β¦972 m
Surplus = (A.V. β A.C.) Γ Q β levies Accounted surplus β¦27.6 m p.a. Revenue β¦972 m β cost β¦780 Γ 1.18 million t = β¦52 m Export charges β¦24.3 m: 15% of export revenue (federal levy and permit fee) Distributed 40% to reinvestment, 20% to the municipal aggregate and 40% swept to the Treasury. = β¦27.6 m
Made from per tonne
Used in p.a.
-
Paper1.18 million tβ¦972 m100%
- Final domestic use 517,600 t β¦426 m 43.9%
- Exports 196,700 t β¦162 m 16.7%